Five Must-Review Contract Provisions

0

Claims and Change Orders: One of the most important and most litigated contract provisions deals with claims and change orders. Contracts typically require a contractor to submit a change order or make a claim within a certain number of days after the occurrence of the event giving rise to the change order or claim.

1. Identifying changes early is critical to protecting the ability to be compensated for added costs.
First notice requirements almost always have short time limits and late notice can eliminate the right to compensation. In addition, prompt action means that events are fresh in everyone’s minds, and gives other parties the opportunity to mitigate the financial and schedule impacts, avoiding end-of-job surprises and lawsuits. Perhaps the most important failure is to follow the claim procedure that may result in the waiver of the claim. Everyone should have working knowledge of the contract’s claim and change order provisions.

2. Supporting Documentation
After safety, identification of the type and content of the documents that must be submitted to receive timely and complete payment or to support a claim or change order is the most important activity on a construction project. Good documentation protects the financial health of the contractors and without it bad things happen. Typical documents include the following: (1) executed payment applications; (2) payroll or progress; (3) payment requests; (4) documents substantiating the payment request; (5) lien waivers; and (6) documentation showing evidence that the submitting contractor has made, or intends to make, payments to its subcontractors or material suppliers. With regard to application for final payment, typical documents accompanying final payment application include the following: (1) as-built drawings; (2) operations and maintenance manuals; (3) manufacturer and other warranty documentation; (4) evidence of necessary start-up testing; and (5) final lien waivers. It is important for all contractors to know and understand the contractually required documents and include all of them in payment applications or claims to ensure timely payment.

3. Certification Requirements
More sophisticated projects, and all government projects, require a contractor to certify certain items with each payment application. These certifications can include certified payroll, as well as ongoing representations about the basis for payment. In some contracts, satisfactory proof of the proper use of prior payments is required before the current request is processed. The consequences of missing or incorrect certifications can be a loss of a deal or payment or more serious fines. In extreme cases contracts can be barred for future government work.

4. Reimbursable Expenses
Cost plus time and materials contracts generally detail allowable or reimbursable cost items. However, the contract may also exclude costs from reimbursement or disallow any markups on certain items. In these types of agreements record keeping is critical, because owners and upstream contractors have the right to audit the downstream contractor’s records to verify expenses. If the downstream contractor overcharged, they will be liable for reimbursing the overcharge with interest. Contracting parties may avoid common disputes that arise over these types of “overhead” costs by agreeing in advance how they will be paid or using a lump sum contract.

5. Indemnification and Insurance
The indemnity and insurance provisions of a construction contract are tremendously important but often receive little to no attention during contract negotiation and drafting. These provisions place the financial responsibility for inherent risks on the downstream contractors. These provisions are viewed as boilerplate in the beginning of the project, but when a claim arises they are hotly contested and can have disastrous ramifications if not properly drafted or followed.
Every contractor should have the indemnity and insurance clauses reviewed annually. These seemingly innocuous contract provisions can shift liability among the parties and the law is constantly changing.

Jacob Zahniser is an attorney in Jordan Ramis PC’s Dirt Law practice group. His practice focuses on construction and real estate litigation, as well as handling insurance coverage disputes arising from construction defects. He can be reached at 541-550-7900 or jacob.zahniser@jordanramis.com.

Share.

About Author

A litigator and trial attorney at Jordan Ramis PC, Jacob Zahniser focuses his practice on construction law and construction and real estate litigation, as well as handling insurance coverage disputes arising from construction defects. He can be reached at 541-550-7900, or via email at Jacob.zahniser@jordanramis.com. www.jordanramis.com

Leave A Reply