Redmond Municipal Airport Runway 4-22 Rehabilitation Project Update

0

The Redmond Municipal Airport re-opened its primary Runway 4-22 after Phase 1 pavement rehabilitation construction was substantially completed. The pavement rehabilitation of Runway 4-22 is a multi-phase project that is part of the City of Redmond’s continuing commitment to provide the highest quality airport facilities and services to the central Oregon region and its air travel needs.

Runway 4-22 Phase 1 construction consisted of: full depth asphalt runway reconstruction of approximately 1,290 feet in length by 150 feet wide, runway drainage improvements, new high-intensity runway lights and grading to improve runway shoulder and runway safety areas. Phase 1 construction required closure of Runway 4-22 and its instrument landing system. This work was completed in 77 days and was within budget.

The remaining Phase 1 construction items require warmer weather and will be completed this coming spring. In the spring of 2015 High Desert Aggregate and Paving (Terrebonne, Oregon) will return to groove runway pavement and apply final paint application bringing Phase 1 to full completion.

The City extends its appreciation to High Desert Aggregate and Paving for their willingness to work with the City’s request to change the project’s original start date from August 18 to September 15 to accommodate aerial firefighting operations conducted by the U.S. Forest Service. They worked evenings, weekends and in a snow storm in order to facilitate the opening of Runway 4-22 for the busy winter season.

Share.

About Author

Founded in 1994 by the late Pamela Hulse Andrews, Cascade Business News (CBN) became Central Oregon’s premier business publication. CascadeBusNews.com • CBN@CascadeBusNews.com

Leave A Reply